Route One

Background watermark

This route provides guidance and templates for procurements that are: 

  • low value (a total estimated value of under £25k inclusive VAT) 
  • low risk and 
  • non-repetitive. 

Route 1 Objectives

What to think about first

Show all sections Hide all sections
Main considerations Show Hide

The main objectives of this Route are to

  • provide a step-by-step guide to conduct a low-value and low-risk procurement exercise;
  • provide a set of guides and templates that can be used to collate and analyse the data required for a Route 1 procurement exercise;
  • standardise the Welsh public sector procurement process across organisations for low value procurements;
  • highlight the minimum legal and policy obligations involved at each stage of the process.

Before you start your Procurement Journey, please consider the following points: 

  1. Is the product/service you are buying business critical? 
  2. Is there a significant risk to your Organisation’s reputation or ability to deliver if something went wrong with what you are buying? 
  3. Is the estimated value of the goods/services that you are buying more than £25,000 over the lifetime of the contract?  If so, this means that Route 1 cannot be used as the contract needs to be advertised and formally tendered. 

To calculate the estimated value of the contract you should add the spend for the full contract duration, including any contract extensions.  

For example, a contract of £10,000 per year (inclusive VAT) over three years plus a 1 year £10,000 extension (inclusive VAT) is a £40,000 contract i.e. 3 x £10,000 + £10,000. 

Splitting contracts

Please note, requirements must not be ‘split’ into contracts of lower value, or contracts reduced in duration, to avoid the need to advertise/conduct a full tender exercise. 

  1. Are existing contracts already available that you could use e.g. call off from? 
  2. Does your Organisation have a lower advertising threshold?  If so, should you follow the Route 2 process?  This information will be held with your Finance Department or Procurement Function. 
  3. Is there a conflict of interest?  Do you or someone in your organisation stand to benefit from the outcome of the procurement?  For example: benefit financially? Have friendships with suppliers? Previously worked for suppliers? If so, should the buyer and/or evaluating team be changed? 

If you have answered ‘yes’ to any of the above questions please contact your local Procurement Function before proceeding. 

What's important Show Hide

Audit Requirements

You should keep a file for your Route 1 procurement documents, in case of future audit. 

You should make sure you are familiar with: 

  • your Organisation’s document retention policy; and 
  • any guidance which may impact on the project before starting. 

Please note that purchases of goods and services may routinely be the subject of Freedom of Information (FoI) requests. 

Quote Distribution, Procurement Documents and Contract Award

Your quote should be sent to the suppliers you want to participate in your quote.  This can be done using the Quick Quote functionality in Sell2Wales or by other means e.g. in writing via email or by post. 

Sell2Wales is recommended as: 

  • you can search through a register of suppliers to select those you want to bid 
  • questions and answers can be provided through this system 
  • this will provide an audit trail for your quote

Procurement Documents  

Your quote should include all of the documents a potential bidder would need to decide whether to bid or not e.g. your specification, and to be able to respond to your quote e.g. a pricing spreadsheet that the bidder needs to complete.  

Prepare Documents provides a checklist of documents that should be included in your quote as a minimum.  

If using Quick Quote in Sell2Wales for your quote, please note that the following file size restrictions apply for uploading documents: 

  • 100Mb  per Notice individual file size is also 100MB  
  • 10Mb per file with a maximum of 30Mb per Supplier     

 

Next steps Show Hide

Once you have completed all stages of your procurement you must seek approval on who to award your quote to.  This approval process must follow your organisation’s governance requirements. 

Once approval has been received you should notify the successful and unsuccessful suppliers of the outcome in writing.  More information, including letter templates, can be found in the Contract Awardsection.  

Do you have what you need? 

Before carrying on, please check you have everything you need: 

  • Budgetary sign off and sponsorship. 
  • Individuals with relevant experience to evaluate responses and write the brief. 
  • Timescale plan. 

This procurement route should only be used by individuals who are authorised to procure for their Welsh public sector organisation. 

Do you meet these requirements?

You do not need extensive purchasing training, however it is assumed that you have an awareness of: 

  • UK regulations; 
  • Welsh regulations; 
  • applicable local procurement policies, guidelines and governance arrangements.  

If your procurement does not meet the above requirements, or you do not have the authority to procure, contact your procurement function. 

Quick fire background watermark

You are now ready to begin Route 1 of the Procurement Journey.

Start Route 1 - Develop

Have your say today

If you’ve come across any good articles, videos or other content you’d like to share with the Cyd community then please get in touch, we’d love to share your content.

Contact us
Cyd site is currently in Beta and this website will be developed as new services are created.